INTRODUCTION TO SOFTWARE ENGINEERING
SOFTWARE PROCESS MODELS
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
Which of the following is not a factor in the failure of the systems developments projects?
|
size of the company
|
|
inadequate user involvement
|
|
failure of systems integration
|
|
continuation of a project that should have been cancelled
|
Explanation:
Detailed explanation-1: -The success of system development is most often gauged by three primary indicators: the number of days of deviation from scheduled delivery date, the percentage of deviation from the proposed budget, and meeting the needs of the client users.
Detailed explanation-2: -A failed systems development project refers to a finished software or hardware project that doesn’t meet the requirements of the customer or the business. It may also refer to a systems development project that remains unfinished due to a lack of resources or funding.