Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
In which phase technical task and schedule for the work to be developed
|
Planning phase
|
|
Analysis phase
|
|
Designing phase
|
|
None of the above
|
Explanation:
Detailed explanation-1: -The planning phase can include the following steps: Deciding on milestones that lead up to goal completion. Developing a schedule for tasks and milestones, including time estimates and potential time buffers. Establishing change processes.
Detailed explanation-2: -Planning, build-up, implementation, and closeout.
Detailed explanation-3: -The project management life cycle is usually broken down into four phases: initiation, planning, execution, and closure. These phases make up the path that takes your project from the beginning to the end.