SOFTWARE ENGINEERING

INTRODUCTION TO SOFTWARE ENGINEERING

WATERFALL MODEL

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Meeting that demonstrates to the product owner and the team what was accomplished during Sprint?
A
Sprint Review/Demo Meeting
B
Sprint Retrospective Meeting
C
Sprint Planning Meeting
D
Stakeholder Review Meeting
Explanation: 

Detailed explanation-1: -The sprint review, or commonly the sprint demo is a meeting that takes place at the end of the sprint, where the team showcases their “potentially shippable product”.

Detailed explanation-2: -In a nutshell, here’s what happens during a sprint review session: The scrum team presents the results of the sprint and all parties collaborate on what should happen next. Next steps may include refining the product backlog to match priorities and conducting a sprint retrospective.

Detailed explanation-3: -The Developers discuss what went well during the Sprint, what problems it ran into, and how those problems were solved; The Developers demonstrate the work that it has “Done” and answers questions about the Increment; The Product Owner discusses the Product Backlog as it stands.

There is 1 question to complete.