INTRODUCTION TO SOFTWARE ENGINEERING
WATERFALL MODEL
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
Problem identification is the ____ and initial phase of the waterfall model.
|
First
|
|
Third
|
|
Second
|
|
None of the above
|
Explanation:
Detailed explanation-1: -A correct order of the waterfall model phases are problem identification, analysis, design, implementation, testing, deployment, and implementation.
Detailed explanation-2: -Phases of waterfall project management differ from one project to another. But generally, you can group the activities of the waterfall approach into five stages: planning, design, implementation, verification, and maintenance.
Detailed explanation-3: -Requirements Analysis. In this phase, all requirements of the project are analysed and documented in a specification document and a feasibility analysis is done to check if these requirements are valid. System Design. Implementation. Testing. Deployment. Maintenance. 29-Sept-2022