REQUIREMENTS ENGINEERING
REQUIREMENTS GATHERING AND ANALYSIS
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
____ is the first step of requirement elicitation
|
Requirements Gathering
|
|
Listing out Requirements
|
|
Identifying Stakeholder
|
|
All of the options are correct
|
Explanation:
Detailed explanation-1: -The first step of requirement elicitation is to identify the stakeholders who will be involved in the project. Stakeholders are individuals or organizations who have an interest in the project’s outcome or who will be affected by the project.
Detailed explanation-2: -The first step is to gather, analyze and develop requirements from the Concept of Operations (CONOPS), stakeholder needs, objectives, and other external requirements.
Detailed explanation-3: -Stakeholders are the people from whom we first elicit requirements, and then from whom we obtain the input necessary during requirements analysis and negotiation, and then who will finally accept the system into service.
There is 1 question to complete.