Risk analysis of a project is done in
A
System Analysis phase
B
Feasibility Study
C
Implementation phase
D
Maintenance phase
Explanation: 

Detailed explanation-1: -As the name implies, a feasibility analysis is used to determine the viability of an idea, such as ensuring a project is legally and technically feasible as well as economically justifiable. It tells us whether a project is worth the investment-in some cases, a project may not be doable.

Detailed explanation-2: -Introduction. As part of the Risk Management process, Risk Analysis is conducted during the Analyzation Stage of the hefty System Development Life Cycle causing the risk analysis stage to often be neglected by IS project managers.

Detailed explanation-3: -Contents of a Feasibility Study Technology Considerations. Product or Service Marketplace. Identification of Specific Market.