Which of the following is not a guideline for successfully conducting a JRP session?
|
Brainstorm technical alternatives to problems identified in a JRP session
|
|
Encourage group consensus
|
|
Allow for breaks
|
|
Apply conflict resolution techniques
|
Explanation:
Detailed explanation-1: -1 Answer. brainstorm technical alternatives to problems identified in a JRP session is NOT a guideline for successfully conducting a Joint Requirements Planning (JRP) session.
Detailed explanation-2: -Definition: JRP (Joint Requirements Planning) Systems planning performed cooperatively by a team of users and technicians. Functions should be prioritized and related to the organization’s goals and business opportunities.