REQUIREMENTS ENGINEERING
REQUIREMENTS GATHERING AND ANALYSIS
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
|
Requirement management
|
|
Requirement Gathering
|
|
Requirement Analysis
|
|
None of the above
|
Detailed explanation-1: -It is a set of activities that help the project team to identify, control and track the requirements and changes can be made to the requirements at any time of the ongoing project. These tasks start with the identification and assign a unique identifier to each of the requirement.
Detailed explanation-2: -Requirements management is the process of documenting, analyzing, tracing, prioritizing and agreeing on requirements and then controlling change and communicating to relevant stakeholders. It is a continuous process throughout a project.
Detailed explanation-3: -Requirements Change Management is the process of identifying, analyzing, tracking, and approving changes to the requirements. The main aim of this process is to minimize the impact of change on the project schedule and costs. It also helps in maintaining the quality of deliverables.
Detailed explanation-4: -There are four main stages of the requirements management process-planning, development, system verification, and system validation-each with important considerations to the overall project.