Which of the following diagram is time oriented?
|
Collaboration
|
|
Sequence
|
|
Activity
|
|
None of the mentioned
|
Explanation:
Detailed explanation-1: -Explanation: A sequence diagram is time-oriented.
Detailed explanation-2: -Sequence Diagrams are time focus and they show the order of the interaction visually by using the vertical axis of the diagram to represent time what messages are sent and when.
Detailed explanation-3: -A sequence diagram is a type of interaction diagram because it describes how-and in what order-a group of objects works together. These diagrams are used by software developers and business professionals to understand requirements for a new system or to document an existing process.
Detailed explanation-4: -Sequence Diagram is an interaction diagram that emphasizes the time ordering of messages sent between objects.