SOFTWARE ENGINEERING

SOFTWARE DESIGN

OBJECT ORIENTED DESIGN

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
During what stage of the RUP process to determine the cost and duration, identify the risks and the system environment?
A
Inception
B
Elaboration
C
Construction
D
Transition
Explanation: 

Detailed explanation-1: -During this phase, the project’s basic ideas and structure will be determined to prepare a business suite, i.e. the team will decide the purpose of the project, success criteria, estimated cost, risk assessment, scheduled time, and resources required to complete it etc.

Detailed explanation-2: -In the inception stage of RUP, you communicate and plan the software concept or idea, evaluating what resources you need for the project and determining if it’s viable. You use case modeling to identify the project scope, costs and time required to build it.

Detailed explanation-3: -The production phase finalizes the rational unified process. This phase involves components you can use when encouraging end-user acceptance, including software employment.

Detailed explanation-4: -Inception phase The primary objective is to scope the system adequately as a basis for validating initial costing and budgets.

There is 1 question to complete.