Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Designing the test environment set-up and identifying any required infrastructure and tools are a part of which phase
A
Test Implementation
B
Test Design
C
Test Completion
D
Test Execution
Explanation: 

Detailed explanation-1: -#1) Designing the test environment set-up and identifying any required infrastructure and tools that are a part of which phase? b) Option b: Analysis and design activities come before implementation. Test environment set-up and identifying any required infrastructure and tools are a part of this activity.

Detailed explanation-2: -Phase 1 – Test Planning and Control Based on this understanding and as a part of test planning, specify the objective of testing, and determine the scope and risk. The next activity is to design test strategy, identify the resource requirements, schedule test analysis, and design tasks.

Detailed explanation-3: -Test implementation and execution has the following major tasks: Developing implementing and prioritizing test cases. Developing and prioritizing test procedures, creating test data. Creating test suites from the test procedures for efficient test execution.

There is 1 question to complete.