In which activity of the Fundamental Test Process is the test environment set up?
A
Test implementation and execution.
B
Test planning and control
C
Test analysis and design
D
Evaluating exit criteria and reporting
Explanation: 

Detailed explanation-1: -Test Planning : Test planning involves producing a document that describes an overall approach and test objectives. It involves reviewing the test basis, identifying the test conditions based on analysis of test items, writing test cases and Designing the test environment.

Detailed explanation-2: -During test implementation and execution, we take the test conditions into test cases and procedures and other testware such as scripts for automation, the test environment and any other test infrastructure.

Detailed explanation-3: -STLC Phases Test Planning − Test Team plans the strategy and approach. Test Case Designing − Develop the test cases based on scope and criteria’s. Test Environment Setup − When integrated environment is ready to validate the product. Test Execution − Real-time validation of product and finding bugs.

Detailed explanation-4: -Developing implementing and prioritizing test cases. Developing and prioritizing test procedures, creating test data. Creating test suites from the test procedures for efficient test execution. Verifying that the test environment has been set up correctly. More items