Which of the following are typical exit criteria for testing?i) costsii) Schedules such as those based on time to marketiii) Test environment availability and readinessiv) Estimates of defect density or reliability measures.
|
i, ii and iii only
|
|
ii, iii and iv only
|
|
i, iii and iv only
|
|
i, ii and iv only
|
Explanation:
Detailed explanation-1: -What is Entry and Exit Criteria? Entry Criteria: Entry Criteria gives the prerequisite items that must be completed before testing can begin. Exit Criteria: Exit Criteria defines the items that must be completed before testing can be concluded.
Detailed explanation-2: -Exit criteria are the criteria or requirements which must be met to complete a specific task or process as used in some fields of business or science, such as software engineering.
Detailed explanation-3: -Testers execute and log the tests, evaluate the results and document problems found. They monitor the testing and the test environment, often using tools for this task, and often gather performance metrics.