SOFTWARE ENGINEERING TOOLS AND ENVIRONMENTS
AUTOMATED TESTING TOOLS
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
Which of the following characteristics and types of review processes belong together?1. Led by the author2. Undocumented3. No management participation4. Led by a trained moderator or leader5. Uses entry and exit criterias. Inspectiont. Technical reviewu. Informal reviewv. Walkthrough
|
s = 4, t = 3, u = 2 and 5, v = 1
|
|
s = 4 and 5, t = 3, u = 2, v = 1
|
|
s = 1 and 5, t = 3, u = 2, v = 4
|
|
s = 5, t = 4, u = 3, v = 1 and 2
|
Explanation:
Detailed explanation-1: -Explanation in favor of the correct answer The correct sequence is: planning, kick-off, individual preparation, review meeting, re-work, follow-up.
Detailed explanation-2: -The formal review follows the formal process which consists of six main phases – Planning phase, Kick-off phase, the preparation phase, review meeting phase, rework phase, and follow-up phase.
Detailed explanation-3: -Planning. Initiate Review. Individual Review or Preparation. Issue Communication and Analysis. Fixing and Reporting. 21-Sept-2020
There is 1 question to complete.