Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Which of the following is the FIRST step of the reengineering process?
A
Identifying the process(es) to be reengineered
B
Analyze them and find any process gaps or disconnects
C
Design a cutting-edge future-state process map
D
Implement future state changes and be mindful of dependencies
Explanation: 

Detailed explanation-1: -Business process reengineering is implemented in 3 phases, analysis, design, and implementation phases. Implementation of all these phases should be followed by communication throughout the organization.

Detailed explanation-2: -"Reengineering” as a business battle cry was first heard in the early 1990s. Most commentators cite publication of a 1993 book by consultants Michael Hammer and James Champy, entitled Reengineering the Corporation, as the important moment when reengineering became a movement.