Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Which of these is most likely to be beneficial in the Design phase?
A
Beta Testing
B
Coding
C
Prototype
D
Flowchart
Explanation: 

Detailed explanation-1: -Identify why you are drawing the Flowchart(s) You may be drawing it to explain a process to someone, to understand a process, to find loopholes in a flow and so on. It is important to identify the objective on why you want a flowchart for this. Understanding the audience is another important thing.

There is 1 question to complete.