SOFTWARE PROJECT MANAGEMENT
CONFIGURATION MANAGEMENT
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
Choose the factors that influence whether or not we want to implement a change after a change request to a software
|
costs of making the change
|
|
number of users making the change
|
|
product release cycle
|
|
benefits of change request
|
Explanation:
Detailed explanation-1: -Answer: D. Submit a change request.
Detailed explanation-2: -Corrective Actions. Preventive Actions. Defect Repairs. 07-Jul-2020