Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Which baselines draw on the functions, identifying the individual components that are needed to perform the functions?
A
Allocated Baseline
B
Functional Baseline
C
Product Baseline
D
Design Baseline
Explanation: 

Detailed explanation-1: -Functional Baseline: initial specifications established; contract, etc. Allocated Baseline: state of work products after requirements are approved. Developmental Baseline: state of work products amid development. Product Baseline: contains the releasable contents of the project.

Detailed explanation-2: -A baseline is a formally accepted version of a software configuration item. It is designated and fixed at a specific time while conducting the SCM process. It can only be changed through formal change control procedures. Activities during this process: Facilitate construction of various versions of an application.