SOFTWARE ENGINEERING

SOFTWARE PROJECT MANAGEMENT

PROJECT PLANNING AND ESTIMATION

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Dave is managing a new project to create a radio-operated model plane. The project budget is set at $200, 000 and the project must be completed within six months of the starting date. The initial document authorizing this project and giving Dave the authority to apply organizational resources to the project activities is called ____
A
Project charter
B
Scope statement
C
Project management plan
D
Organizational process assets
Explanation: 

Detailed explanation-1: -(41) Which of the following methods is least likely to be used for explaining project planning guidelines to the team? Hint − A report gives information about what happened and doesn’t talk about planning or give guidelines or directives.

Detailed explanation-2: -Monitoring activities include measuring, collecting, and distributing performance information, and controlling activities include determining corrective or preventive actions.

Detailed explanation-3: -The conclusion of a project phase is generally marked by a review of both key deliverables and project performance to date, to a) determine if the project should continue into its next phase and b) detect and correct errors cost effectively.

There is 1 question to complete.