Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Describing stakeholders based on their power (ability to impose will), urgency (need for immediate attention), and legitimacy (their involvement), describes what type of grid or model?
A
Power/Influence grid
B
Salience Model
C
Influence/Impact grid
D
Power model
Explanation: 

Detailed explanation-1: -Salience Model: describing classes of stakeholders based on their power (ability to impose their will), urgency (need for immediate attention), and legitimacy (their involvement is appropriate).

Detailed explanation-2: -Dominant: These stakeholders have high power and legitimacy, but low urgency. Their power and legitimacy make them important for project success, but their low urgency means they may not have to be part of the core project effort. Dangerous: These stakeholders have high power and urgency, but low legitimacy.

Detailed explanation-3: -Urgency: A stakeholder with urgency has critical needs that require immediate attention. For example, a pharmaceutical company that creates lifesaving medicines might consider their customers to be stakeholders with urgency, because their health is affected by the availability and effectiveness of the drugs.

Detailed explanation-4: -The power/interest grid is a matrix used for categorising stakeholders during a change project to allow them to be effectively managed. Stakeholders are plotted on the grid in relation to the power and interest they have in respect of the project.