Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
In function point analysis, number of Complexity adjustment factor are
A
10
B
20
C
14
D
12
Explanation: 

Detailed explanation-1: -The complexity adjustment factor (CAF) is based on 14 general system characteristics (GSC’s) that rate the general functionality of the application being counted. Each characteristic has associated descriptions that help determine the degrees of influence of the characteristics.

Detailed explanation-2: -4. Value Adjustment Factor: In this step the value adjustment factor is determined. VAF contains 14 General system characteristics(GSC) of the system or application that defines the types of application characteristics and is rated on a scale of 0 to 5.

Detailed explanation-3: -The Value Adjustment Factor (VAF) is based on 14 GSCs that rate the general functionality of the application being counted. GSCs are user business constraints independent of technology. Each characteristic has associated descriptions to determine the degree of influence.