Stakeholder management is a critical aspect of managing a project. In order to manage stakeholder expectations, the project manager must come up with a strategy. One technique that can be used to develop this strategy is the ____
A
Issue log check
B
Stakeholder analysis
C
Stakeholder register
D
Stakeholder management plan
Explanation: 

Detailed explanation-1: -Identify Stakeholders. Before you can manage your stakeholders’ expectations, you need to know who your stakeholders are. Manage Stakeholders Differently. Keep Stakeholders in the Loop. Share Evidence and Research. Produce Value Regularly. Track Sentiment.

Detailed explanation-2: -Stakeholder identification. The first and most important step is to pin down both internal and external stakeholders. Setting up a stakeholder engagement plan. Continuous stakeholder interaction. Reporting back to stakeholders. 21-Oct-2021