SOFTWARE PROJECT MANAGEMENT
PROJECT PLANNING AND ESTIMATION
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
Static multi-variable model was developed by
|
SEL
|
|
W-F
|
|
Boehm
|
|
None of these
|
Explanation:
Detailed explanation-1: -A dynamic multivariate model projects resource requirements as a fnnction of time. A theoretical approach to dynamic multivariable modeling hypothesizes a continuous resource expenditure curve and from it, derives equations that model the behavior of the resource.
Detailed explanation-2: -Effort estimation is the process of forecasting how much effort is required to develop or maintain a software application.
There is 1 question to complete.