What is the first activity in Software Project Planning?
A
Determination of software scope
B
Determination of budget
C
Find out the team size
D
None of these
Explanation: 

Detailed explanation-1: -Explanation: The first step in project planning is to establish the objectives and scope.

Detailed explanation-2: -The first activity in software development is the analysis part. In the OOA model, (Object-Oriented Analysis), the requirements are oriented around objects integrating both processes and data.

Detailed explanation-3: -Step 1: Get an understanding of the subject matter. Step 2: Define the project goal. Step 3: Make a list of tasks and deliverables. Step 4: Identify the project stakeholders.

Detailed explanation-4: -Define stakeholders. Stakeholders include anyone with an interest in the project. Define roles. Each stakeholder’s role should be clearly defined. Introduce stakeholders. Set goals. Prioritize tasks. Create a schedule. Assess risks. Communicate. More items