What is the main objective of Software Project Planning?
A
Estimation of resources
B
Estimation of cost
C
Estimation of schedule
D
All of the above
Explanation: 

Detailed explanation-1: -The objective of software project planning is to provide a framework that enables the manager to make reasonable estimates of resources, cost, and schedule. These estimates are made within a limited time at the beginning of a software project and should be updated regularly as the project progresses.

Detailed explanation-2: -In brief, project management objectives are the successful development of the project’s procedures of initiation, planning, execution, regulation and closure as well as the guidance of the project team’s operations towards achieving all the agreed upon goals within the set scope, time, quality and budget standards.