SOFTWARE ENGINEERING

SOFTWARE PROJECT MANAGEMENT

PROJECT PLANNING AND ESTIMATION

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Which of the following is the most accurate cost estimate method?
A
Rough Order
B
Three-Point
C
Parametric
D
Bottom-up
Explanation: 

Detailed explanation-1: -Conclusion. The estimation method that is the most accurate is called bottom-up estimation. In addition to providing an estimate of the resources, amount of time, and costs associated with the planned work, this method can also be used to evaluate change requests.

Detailed explanation-2: -Accuracy of Bottom-up Estimates The bottom-up estimation technique is also referred to as deterministic or detailed estimating. It is often used as the so-called “definitive estimate” – a type of cost estimate that comes with an accuracy between-5% and +10% according.

Detailed explanation-3: -Bottom-up estimating allows team members to see all the components of a project in one place, and it saves them time and effort by estimating separately. Saves time. By estimating the work package in advance, a manager can make better decisions and avoid costly mistakes. It also helps avoid surprises down the road.

Detailed explanation-4: -What Is Bottom-Up Estimating? Also known as the deterministic, definitive or detailed estimate, it is a project management methodology approved by Project Management Institute. It ensures to cover each detail for accurate estimation of cost, duration or resources required for the project or its parts.

There is 1 question to complete.