Which of the following processes of Scope Management Process provides confirmation and formal acceptance that the project’s scope is accurate, complete, and supports the project’s goal?
|
Collect Requirement
|
|
Define Scope
|
|
Create Work Breakdown Structure
|
|
Validate Scope
|
|
Control Scope
|
Explanation:
Detailed explanation-1: -It is when the project customer formally accepts all the project deliverables. This process occurs at the end of each phase.
Detailed explanation-2: -Scope verification involves formal acceptance of the completed project scope by the stakeholders. This acceptance is often achieved by a customer inspection and then sign-off on key deliverables.
Detailed explanation-3: -Scope validation is the process of formalizing acceptance of completed project deliverables and ensuring the output meets all the requirements/standards set at the beginning. This includes validating the deliverable with the customer or the sponsor, and getting the acceptance from the customer or the sponsor.