Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Which of the following processes of Scope Management Process provides confirmation and formal acceptance that the project’s scope is accurate, complete, and supports the project’s goal?
A
Collect Requirement
B
Define Scope
C
Create Work Breakdown Structure
D
Validate Scope
E
Control Scope
Explanation: 

Detailed explanation-1: -It is when the project customer formally accepts all the project deliverables. This process occurs at the end of each phase.

Detailed explanation-2: -Scope verification involves formal acceptance of the completed project scope by the stakeholders. This acceptance is often achieved by a customer inspection and then sign-off on key deliverables.

Detailed explanation-3: -Scope validation is the process of formalizing acceptance of completed project deliverables and ensuring the output meets all the requirements/standards set at the beginning. This includes validating the deliverable with the customer or the sponsor, and getting the acceptance from the customer or the sponsor.