Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Which of the following stakeholder makes the details of scope in a project?
A
Project team
B
Project Manager
C
Project Sponsor
D
None of the above
Explanation: 

Detailed explanation-1: -Defining project scope requires input from the project stakeholders. They work with project managers to establish the key elements of budget, objectives, quality and timeline. To determine scope, project managers must collect requirements for what the stakeholders need from the project.

Detailed explanation-2: -Scope refers to the detailed set of deliverables or features of a project. These deliverables are derived from a project’s requirements. PMBOK® defines Project Scope as the “The work that needs to be accomplished to deliver a product, service, or result with the specified features and functions.”

Detailed explanation-3: -Stakeholders are those with an interest in your project’s outcome. They are typically the members of a project team, project managers, executives, project sponsors, customers, and users.

Detailed explanation-4: -A project manager, with input from key stakeholders, is usually responsible for defining project scope. Stakeholder needs are often a key influence on the scope of a project. It is often the project manager’s job to factor in the human and financial resources they need to meet these requirements.