Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
Activity A has a duration of three days and begins on the morning of Monday the 4th. The successor activity, B, has a finish-to-start relationship with A. The finish-to-start relationship has three days of lag, and activity B has a duration of four days. Sunday is a non-workday. Such data can help to determine-
|
The total duration of both activities is 8 days
|
|
Calendar time between the start of A to the finish of B is 11 days
|
|
The finish date of B is Wednesday the 13th
|
|
Calendar time between the start of A to the finish of B is 14 days
|
Explanation: