Activity A has a pessimistic (P) estimate of 36 days, a most likely (ML) estimate of 21 days, and an optimistic (O) estimate of 6 days. What is the probability that activity A will be completed in 16 to 26 days?
|
55.70 percent
|
|
68.26 percent
|
|
95.46 percent
|
|
99.73 percent
|
Explanation: