Activity A has a pessimistic (P) estimate of 36 days, a most likely (ML) estimate of 21 days, and an optimistic (O) estimate of 6 days. What is the probability that activity A will be completed in 16 to 26 days?
A
55.70 percent
B
68.26 percent
C
95.46 percent
D
99.73 percent
Explanation: 