Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
|
Fast tracking
|
|
CPM
|
|
PDM
|
|
Crashing
|
Detailed explanation-1: -Crashing is the technique of shortening the schedule duration by adding more resources (usually people / money or both) to Critical path Activities. There is no change to Scope.
Detailed explanation-2: -To decrease a project’s duration with crashing, a project manager will add appropriate skilled project resources to the project’s critical tasks. Adding resources to non-critical tasks will not affect the timeline. In project management, each project has a triple constraint consisting of schedule, cost, and scope.
Detailed explanation-3: -The term “crashing the schedule” is used in project management to describe a situation where a project’s standard progress is modified to speed up the overall timeline. This can be done by adding more resources, working longer hours, or making other changes to the original project baseline.