An activity in a network has the following characteristics:ES = 12, EF = 22, and LS = 14. ES and LS relate to the beginning of the week, whereas EF relates to the end of the week. The duration of the activity is:
|
8.0 weeks.
|
|
11.0 weeks.
|
|
12.0 weeks.
|
|
14.0 weeks.
|