SOFTWARE ENGINEERING

SOFTWARE PROJECT MANAGEMENT

PROJECT SCHEDULING AND TRACKING

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
As one of the tools and techniques of the Sequence Activities process, a lead:
A
Directs a delay in the successor activity.
B
Could be accomplished by a finish-to-start relationship with a delay time.
C
Means that the successor activity cannot start until after the predecessor is completed.
D
Is the amount of time whereby a successor activity can be started before the previous activity is completed.
Explanation: 

Detailed explanation-1: -Which of the following is true related to activities on the critical path? Delays in these activities will delay in the entire project.

There is 1 question to complete.