As one of the tools and techniques of the Sequence Activities process, a lead:
|
Directs a delay in the successor activity.
|
|
Could be accomplished by a finish-to-start relationship with a delay time.
|
|
Means that the successor activity cannot start until after the predecessor is completed.
|
|
Is the amount of time whereby a successor activity can be started before the previous activity is completed.
|
Explanation:
Detailed explanation-1: -Which of the following is true related to activities on the critical path? Delays in these activities will delay in the entire project.