Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
|
You have a fragnet.
|
|
There can be multiple predecessors for some tasks.
|
|
Several identical or nearly identical series of activities are repeated throughout the project.
|
|
There are too many successors.
|
Detailed explanation-1: -Sequencing is the order of tasks to be done in chain. Hence the next task is started once the previous one is completed. Scheduling, on the other hand is the process in which people are assigned to time to accomplish different tasks. It improves the delivery performance and reduces the manufacturing time and cost.
Detailed explanation-2: -Mathematical analysis. Using mathematical logic, you can calculate your project timeline with all the factors of your project scope considered. Duration compression. Simulation. Resource-leveling heuristics. Gantt charts. Task lists. Calendar.
Detailed explanation-3: -Stop/prevent all scope changes. Downward adjust the scope of work. Re-evaluate activities yet to be done. Develop a new viable/realistic schedule. Develop a risk management plan. Re-evaluate resource availability. Develop new project planning documents. 29-Jan-2015