Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
If, when developing your project schedule, you want to define a distribution of probable results for each schedule activity and use that distribution to calculate another distribution of probable results for the total project, the most common technique to use is-
A
What-if scenario analysis
B
Monte Carlo analysis
C
Linear programming
D
Concurrent engineering
Explanation: 