SOFTWARE ENGINEERING

SOFTWARE PROJECT MANAGEMENT

PROJECT SCHEDULING AND TRACKING

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
It is important to use the critical path method in Control Schedule because-
A
It assists in reviewing scenarios to bring the schedule in line with the plan
B
It enables a consideration of the resource availability and the project time
C
It examines project performance over time
D
It can help identify schedule risks
Explanation: 

Detailed explanation-1: -Using the critical path method is important when managing a project because it identifies all the tasks needed to complete the project, then determines the tasks that must be done on time, those that can be delayed if needed and how much float or slack you have.

There is 1 question to complete.