SOFTWARE ENGINEERING

SOFTWARE PROJECT MANAGEMENT

PROJECT SCHEDULING AND TRACKING

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Project A has an internal rate of return (IRR) of 21 percent. Project B has an IRR of 7 percent. Project C has an IRR of 31 percent. Project D has an IRR of 19 percent. Which of these would be the best project?
A
Project A
B
Project B
C
Project C
D
Project D
Explanation: 

Detailed explanation-1: -The IRR rule states that if the IRR on a project or investment is greater than the minimum RRR-typically the cost of capital, then the project or investment can be pursued. Conversely, if the IRR on a project or investment is lower than the cost of capital, then the best course of action may be to reject it.

Detailed explanation-2: -The Internal Rate of Return (IRR) is the discount rate that makes the net present value (NPV) of a project zero. In other words, it is the expected compound annual rate of return that will be earned on a project or investment.

There is 1 question to complete.