The client demands changes to the product specification that will add only two weeks to the critical path. Which of the following is the best thing for the project manager to do?
A
Compress the schedule to recover the two weeks.
B
Cut scope to recover the two weeks.
C
Consult with the sponsor about options.
D
Advise the client of the impact of the change.
Explanation: 

Detailed explanation-1: -139 The client changes the product specification that will add only two weeks to the critical path. Which of the following is the best thing for the project manager to do? Compress the schedule to recover the two weeks.

Detailed explanation-2: -When it comes to changes, the project manager’s attention is BEST focused on: Making changes. Tracking and recording changes.

Detailed explanation-3: -Which of the following BEST describes what a project charter may be used for when the work is being completed? Explanation: One of the ways to decide if a change should be approved is to determine whether the work falls within the project charter.

Detailed explanation-4: -Answer is (D) Work to prevent changes It is important for project managers that the project baseline is not being changed fr…