Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
The customer has accepted the completed project scope. However, the lessons learned required by the project management office have not been completed. What is the status of the project?
A
The project is incomplete because it needs to be replanned.
B
The project is incomplete until all project and product deliverables are complete and accepted.
C
The project is complete because the customer has accepted the deliverables.
D
The project is complete because it has reached its due date.
Explanation: 

Detailed explanation-1: -69 A project team has completed, and the customer has accepted, the completed project scope. However, the lessons learned required by the project management office have not been completed. What is the status of the project? The project is incomplete because the project needs to be re-planned.

Detailed explanation-2: -Project scope describes what you expect to deliver to your customers when the project is complete. An expected output over the life of a project would be classified as a target.

Detailed explanation-3: -Validate Scope is the process of formalizing acceptance of the completed project deliverables. The key benefit of this process is that it brings objectivity to the acceptance process and increases the chance of final product, service, or result acceptance by validating each deliverable.