Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
The precedence diagramming method (PDM) shows:
A
Various levels of the work breakdown structure.
B
Activities likely to be involved in project integration and resource allocation processes.
C
The logical relationships that exist between activities.
D
The project completion date based on normal resource availability.
Explanation: 

Detailed explanation-1: -Finish-to-Start, Start-to-Start, Finish-to-Finish, Start-to-Finish. 24-Dec-2022

Detailed explanation-2: -The 4 types of logical relationships in the precedence diagraming method are: Finish-to-Start (FS) dependency, Finish-to-Finish (FF) dependency, Start-to-Start (SS) dependency, and.

Detailed explanation-3: -In PDM, finish-to-start is the most commonly used type of precedence relationship.

Detailed explanation-4: -There are four possible activity relationships, which are defined in the Project Management Institute’s “bible of project management”-The Project Management Body of Knowledge (PMBOK®). The relationships are Finish-to-Start, Start-to-Start, Finish-to-Finish and Start-to-Finish.