Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
The precedence diagramming method (PDM) shows:
|
Various levels of the work breakdown structure.
|
|
Activities likely to be involved in project integration and resource allocation processes.
|
|
The logical relationships that exist between activities.
|
|
The project completion date based on normal resource availability.
|
Explanation:
Detailed explanation-1: -Finish-to-Start, Start-to-Start, Finish-to-Finish, Start-to-Finish. 24-Dec-2022
Detailed explanation-2: -The 4 types of logical relationships in the precedence diagraming method are: Finish-to-Start (FS) dependency, Finish-to-Finish (FF) dependency, Start-to-Start (SS) dependency, and.
Detailed explanation-3: -In PDM, finish-to-start is the most commonly used type of precedence relationship.
Detailed explanation-4: -There are four possible activity relationships, which are defined in the Project Management Institute’s “bible of project management”-The Project Management Body of Knowledge (PMBOK®). The relationships are Finish-to-Start, Start-to-Start, Finish-to-Finish and Start-to-Finish.