The project was going well when all of a sudden there were changes to the project coming from multiple stakeholders. After all the changes were determined, the project manager spent time with the stakeholders to find out why there were changes and to discover any more. The project work had quieted down when a team member casually mentioned to the project manager that he added functionality to a product of the project. “Do not worry, “ he said, “I did not impact, schedule, cost, or quality!” What should the project manager do first?
A
Ask the team member how the need for the functionality was determined.
B
Hold a meeting to review the team member’s completed work.
C
Look for other added functionality.
D
Ask the team member how he knows there is no schedule, cost, or quality impact.
Explanation: 

Detailed explanation-1: -Answer is (D) Work to prevent changes It is important for project managers that the project baseline is not being changed fr…

Detailed explanation-2: -Project Performance: This monitors changes in the project. It takes into consideration the amount and types of issues that arise and how quickly they are addressed. These can occur from unforeseen hurdles and scope changes.