Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Three-point estimating uses:
A
An optimistic, pessimistic, and most likely estimate to calculate the estimate.
B
The weighted average of optimistic, pessimistic, and most likely estimates to calculate the expected duration of the activity.
C
Dummy activities to represent logic links among three or more activities.
D
Free float instead of total float in the schedule calculations.
Explanation: 

Detailed explanation-1: -Step 1 − Arrive at the WBS. Step 2 − For each task, find three values − most optimistic estimate (O), a most likely estimate (M), and a pessimistic estimate (L). Step 3 − Calculate the Mean of the three values. Step 5 − Calculate the Standard Deviation of the task.