Three-point estimating uses:
|
An optimistic, pessimistic, and most likely estimate to calculate the estimate.
|
|
The weighted average of optimistic, pessimistic, and most likely estimates to calculate the expected duration of the activity.
|
|
Dummy activities to represent logic links among three or more activities.
|
|
Free float instead of total float in the schedule calculations.
|
Explanation:
Detailed explanation-1: -Step 1 − Arrive at the WBS. Step 2 − For each task, find three values − most optimistic estimate (O), a most likely estimate (M), and a pessimistic estimate (L). Step 3 − Calculate the Mean of the three values. Step 5 − Calculate the Standard Deviation of the task.