SOFTWARE ENGINEERING

SOFTWARE PROJECT MANAGEMENT

PROJECT SCHEDULING AND TRACKING

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Which statement is FALSE about Critical Path?
A
The longest path on network diagram
B
The path that represent the shortest time in which a project could be finished.
C
The shortest path on network diagram
D
None of the above
Explanation: 

Detailed explanation-1: -Misconception: The critical path is the shortest path through the network diagram. Fact: The critical path is the longest path through the network diagram, meaning the sequence of activities that collectivity define the starting and ending dates for the project and have no slack or float time (excess time).

Detailed explanation-2: -Statement I & IV: True The critical path is the sequence of critical activities that represents the longest path through a project, which determines the shortest possible project duration, if any one activity on critical path delays, it will impact the project completion date.

Detailed explanation-3: -Q:Which of the following isnottrue of the critical path? It has zero float. It’s the shortest activity sequence in the network. You can determine which tasks can start late without impacting the project end date.It controls the project finish date.

Detailed explanation-4: -The critical path (or paths) is the longest path (in time) from Start to Finish; it indicates the minimum time necessary to complete the entire project.

There is 1 question to complete.