Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
You are managing a project that will use a virtual team with team members on three different continents. Your company is looking to use the virtual team to provide a lower cost product by using resources in countries that have a favorable exchange rate to that of your country. To assist in this process as you estimate resource requirements, it is helpful to consider-
A
Bottom-up estimating
B
Reserve analysis
C
Analogous estimating
D
Assumptions analysis
Explanation: 

Detailed explanation-1: -Answer and Explanation: The answer is B. Developing trust and establishing effective patterns of communication. Virtual project teams are accompanied with the challenge of creating connection in the absence of proximity.

Detailed explanation-2: -Use the best communication technologies. Treat time zones fairly. Clarify tasks and processes, not just goals and roles. Don’t forget face-to-face time. More items

There is 1 question to complete.