Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
You are the project manager for the POL Project. This project will use a three-point estimate to calculate the estimates for activity duration. For Activity D, you have the following information:P = 9 weeks, O = 4 weeks, M = 5 weeks. What is the result of this estimate?
|
18 weeks
|
|
6 weeks
|
|
33.33 days
|
|
3 weeks
|
Explanation:
Detailed explanation-1: -The planning phase is when the project plans are documented, the project deliverables and requirements are defined, and the project schedule is created. It involves creating a set of plans to help guide your team through the implementation and closure phases of the project.
Detailed explanation-2: -Early Start of the activity = Early Finish of predecessor activity + 1. Early Finish of the activity = Activity duration + Early Start of activity – 1. 01-Oct-2022