Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
Your well-planned project is likely to encounter a number of change requests and approved changes during its life cycle. In the change management plan, you have outlined the processes that you and others will use to understand the impacts of changes. Getting stakeholder acceptance of the decisions related to change on this project is critical, as a failed project could impact shareholder value and the earning projections for the organization. Your attention is best focused on which of the following regarding changes on your project?
|
Making changes
|
|
Tracking and recording changes
|
|
Informing the sponsor of changes
|
|
Preventing unnecessary changes
|
Explanation:
Detailed explanation-1: -Which of the following are included in the change management process when any change is requested by the key stakeholder in a project? Coordinate and communicate with the appropriate stakeholders. Evaluate the impact and justification of the change.
Detailed explanation-2: -14. When it comes to changes, the project manager’s attention is BEST focused on: Making changes. Tracking and recording changes.
Detailed explanation-3: -The correct answer is (C) Create a WBS. WBS allows to break a project into manageable units by all team members, each level of the WBS for deepening the details of the tasks to final level: the concrete tasks to perform .