Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
.... is not a process tools for TQM systems.
A
Process flow analysis
B
Histograms
C
Plier
D
Control charts
Explanation: 

Detailed explanation-1: -Which of the following is not a characteristic of Total Quality Management? Explanation: TQM focuses on customer needs, continuous improvements, and quality circles. Waste reduction is a quality of lean manufacturing, not TQM.

Detailed explanation-2: -Pareto Principle. Scatter Plots. Control Charts. Flow Charts. Cause and Effect, Fishbone, Ishikawa Diagram. Histogram or Bar Graph. Check Lists. Check Sheets.

Detailed explanation-3: -Customer-focused: The customer ultimately determines the level of quality. Total employee involvement: All employees participate in working toward common goals. Process-centered: A fundamental part of TQM is a focus on process thinking. More items

There is 1 question to complete.