SOFTWARE ENGINEERING

SOFTWARE PROJECT MANAGEMENT

QUALITY MANAGEMENT

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
All of the following are considerations for tailoring in Project Quality Management EXCEPT:
A
Standards are regulatory compliance.
B
Policy compliance and auditing.
C
Continuous improvement.
D
Stakeholder management.
Explanation: 

Detailed explanation-1: -The importance of stakeholders’ needs and expectations is limited to the beginning of a project. Project procurement management primarily involves identifying stakeholder needs while managing their engagement throughout the life of the project.

Detailed explanation-2: -Resource Planning. Estimate Resources / Resource Allocation. Acquire Resources. Develop and Manage The Team. Continuously Evaluate Resources.

There is 1 question to complete.