Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
All of the following are signs that a process is out of control, except:
A
A data point exceeds the control limit
B
The customer’s acceptable quality limit is not normally distributed
C
Seven consecutive measurements are below the mean
D
Seven consecutive measurements are above the mean
Explanation: 

Detailed explanation-1: -A Control Chart Indicates a Process is Out of Control When: The following point to out of control conditions on a control chart: Six consecutive points, increasing or decreasing. Fourteen consecutive points that alternate up and down. One or more points outside the control limits.

Detailed explanation-2: -X-Chart. X-Charts present variable data. P-Chart. P-Charts are used for data that is counted. NP-Chart. NP-Charts are used to present the number of nonconforming or conforming items. C-Chart. U-Chart. MR-Chart. Individual MR-Chart. Custom Data Control Chart.