All of the following result from quality audits EXCEPT:
|
Determination of whether project activities comply with organizational policies
|
|
Improved processes to increase productivity
|
|
Creation of quality metrics
|
|
Confirmation of the implementation of approved change requests
|
Explanation:
Detailed explanation-1: -The goal of the project quality management should be clearly shared with all stakeholders, and appropriate tasks should be delegated to those responsible. Quality assurance: This involves auditing the quality requirements and quality control results to ensure appropriate quality standards are used.
Detailed explanation-2: -Perform Quality Assurance is the process of auditing the quality requirements and the results from quality control measurements to ensure appropriate quality standards and operational definitions are used.